8796 full-size modules are required on the entire CE-H detector of which

The cost of consumables and disposable items (HEPA filters, glue, epoxy, cleanroom overalls, gloves, galoshes, etc.) is borne by the project at an estimated cost of $34k per year based on prototyping experience we assume a total of about 18 months of active cleanroom usage during module production.

Prototype-2 also called Pre-series

  • For both prototype cycles we account for technicians for module assembly on the gantry and wire-bonding, as well as a senior electrical engineer for assembly oversight.

PreProduciton

The pre-production of standard modules will consist of 240 modules (about 5%)

Production

12 modules / day

  • 1 FTE (senior engineer) for module QC, rework, supervising technicians, students, overall work oversight, and scheduling of workflow, (JS)
  • 1 FTE (junior technician) for module assembly on the gantry, (JR)
  • 1 FTE (senior technician) for wire-bonding modules, (AS)
  • 1 FTE (junior technician) for encapsulation and support operations on gantry and wire-bonder (Josh)
  • 1 FTE (junior technician) for receiving, inspection, stocking of parts, packing of completed modules, shipping, and overall cleanroom maintenance, (OP)
  • 2 FTE (undergraduate student) for module QC: single module testing, multi module tests including thermal cycling, data analysis, database entry,
  • 1 FTE (graduate student - uncosted) supporting multi module testing and thermal cycling
  • 0.5 FTE (postdoc - uncosted) to supervising undergrads & analyze collected QC data, trend analysis
  • 0.25 FTE (scientist - uncosted) for associated work oversight work

2026-02-26_22-43-27_screenshot.png

The CMU module assembly site will produce 12 modules per day for a total of 324 modules per 8% batch

8% batches are arranged in blocks of 30 days duration each containing 27 days of effort

a 11 such 8% blocks of production plus durations of 15 and 20 days (107 and 123 hours) of labor for the 6-8% and 97-100% batches, respectively.

n of ~70 (~7) weeks corresponding to 2464 (123) labor hours for the production of the 3696 (184) standard production (test-beam) modules